ESeal HP Patch Enables Finalizing the Fracturing Program

Summary:

The challenge was to cover and isolate a hole in the vertical section of a horizontal well to continue with the planned high-pressure 14-stage fracturing program.

Download

Overview
Document Type
Case History
Date Published
Tuesday, May 1, 2012
Region
North America, USA, TX

Additional Document Information

Environment:
Land
System Plan:
Planned
System Type:
ESeal, ESeal HP Patch
Values Added:
Restore production, Extended well life, NPT reduced, Maximize Recoverable reserves, Avoid replacement well/sidetrack
Casing Size:
4 1/2"
Expandable Size:
3 1/2"
Liner Length:
<250'