A major Operator in the Anadarko Basin of Oklahoma lost pressure integrity during completion / frac operation.  A 3-1/2" ESeal HP Liner straddled the parted packer, restoring pressure integrity, and enabling the Operator to continue their completion / frac operations

Download

Overview
Document Type
Case History
Date Published
Tuesday, May 26, 2015
Region
North America, USA, OK

Additional Document Information

Environment:
Land
System Plan:
Planned
System Type:
ESeal, ESeal HP Liner
Values Added:
Enable planned completion, Maximize production, NPT reduced, Avoid replacement well/sidetrack
Casing Size:
4 1/2"
Expandable Size:
3 1/2"
Liner Length:
<250'