05/05/2006

Get back on planned drilling program and finish the well with an adequate hole size to evaluate potential production zones at TD.

11/09/2006

Install a high-collapse SET® expandable liner to case off the trouble zone.

09/30/2000

As the oil and gas industry has matured, three broadreaching and long-standing issues that affect virtually every well have assumed heightened importance: conservation of hole size, hydraulic isolation of selected zones, and maximization of well life. All of these issues involve one of the...

05/07/2010
  • Operator was experiencing trouble formation caused by narrow pore pressure/fracture gradient window which caused casing to be set higher than planned.
  • Operator decided that expandables were the way to go.
  • All of the customer's operating objectives were met.
03/13/2012
An operator drilling a sub-salt exploration deepwater well in Gulf of Mexico, experienced an unstable wellbore at the base of the salt; which resulted in setting the 9-7/8 in. liner 3,400 ft higher than originally planned.
In exploratory wells, maintaining hole size is critical due...
09/19/2006

Leverage information gained from the first well in the development project and install Solid Expandable Tubular (SET®) systems to the subsequent wells to save casing points and preserve hole size while drilling through shale formations and depleted zones.

03/03/2005

Preserve hole size by implementing a contingency plan that included two SET® solid expandable liners and one conventional API liner run below the well’s planned 11-7/8 in. drilling liner.

02/01/2013

A large independent Operator discovered several leaks and a parted section in the 7 in. production casing from 2,000 ft. to 500 ft. In order to fracture the well, casing integrity had to be restored to handle over 6,000 psi surface fracture pressure to ensure the well could become a viable asset...