Challenge: Design and implement a field-level remediation plan using cased-hole SET® Solid Expandable Tubular technology to facilitate production restoration.

05/05/2009

To completely isolate the main pay zone (MPZ) from lower residual oil zone (ROZ) with options to set conventional liner in future if needed for conformance work. Installation of 5-1/2” x 7”, 23 lb ESeal Liners to isolate the upper perforations in each well would enable injection through newly-...

11/21/2013

An Operator, in the Permian, discovered they did not obtain cement coverage along the entire length of the lateral after cementing their production casing.

02/18/2015

A major Operator in the Marcellus required a solution to seal squeeze perforations which would have to withstand high pressure frac operations. The area Regulatory Agency had suspended operations, not allowing completion of the well due to poor cement behind the production casing. The Operator...