Challenge: Design and implement a field-level remediation plan using cased-hole SET® Solid Expandable Tubular technology to facilitate production restoration.

01/05/2008

In order to facilitate a lower zone fracture treatment, three sets of perforations required a high-pressure, gas-tight isolation treatment that would maximize casing ID for completion tools. The solution provided a successful, gas-tight isolation of the three sets of perforations...

10/12/2008

Isolate multiple zones while maximizing diameter by installing a SET Open-hole Liner with swellable elastomers. The maximum diameter would help reduce fluid friction during high-rate fracturing operations.

12/16/2007

Implement an ESeal solution that would enable targeted completion with packer seats while also repairing the damaged vertical section of casing in the Barnett.

05/05/2009

To completely isolate the main pay zone (MPZ) from lower residual oil zone (ROZ) with options to set conventional liner in future if needed for conformance work. Installation of 5-1/2” x 7”, 23 lb ESeal Liners to isolate the upper perforations in each well would enable injection through newly-...

07/16/2010

A leading onshore natural gas producer working Northern Louisiana experienced problems along the vertical section of a horizontal development well.

Enventure deployed two ESeal Liners enabling them to continue the planned completion.

03/01/2010

Enventure's 4-1/4 x 5-1/2 inch, 17 lb/ft ESeal Liner was installed in a Barnett Shale 3000 ft lateral wellbore to isolate existing perforations while allowing fracturing of new shale colume between old perforation clusters.

12/28/2011

The Operator had two sections of perforations in 4-1/2 in. casing that needed to be repaired. They required a solution that would repair the 4-1/2 in. casing and still maintain sufficient ID for this well to be used as a power water injector well.

12/07/2007

As part of a multi-well program, isolate severe water-thief zones in a field where squeezing, casing patches and dual packer isolation assemblies rarely worked. The solution increased production and ultimately resulted in higher reserves.