A leading onshore natural gas producer working Northern Louisiana experienced problems along the vertical section of a horizontal development well.

Enventure deployed two ESeal Liners enabling them to continue the planned completion.

06/01/2018

ESeal™ HP Patch systems: A high-performance wellbore repair solution.

These systems utilize a higher yield-strength material than standard ESeal systems. The material’s increased burst and collapse ratings provide enhanced performance and reliability.

From re-completions to field...

05/30/2018

The ESeal Flex expandable system is an expandable solution primarily designed for well completions, stimulations, and workovers.

06/01/2018

In cased-hole environments, ESeal Liner systems provide a solution to mitigate troubled casing intervals in onshore and offshore applications.

10/15/2014

SET technology is the result of a cold-working process that permanently deforms the pipe without any additional heat. The procedure inherent to expanding tubulars takes the steel beyond its elastic limit into the plastic region of the stress-strain curve, while remaining safely below ultimate...

09/01/2013
In the Marcellus Shale, fracturing rates and pressures can be substantial, but there are other problems also associated with completing these wells, which can promote casing failure or compromise the pressureintegrity of a well. A...
06/01/2018

The ESeal Patch is a single-joint, solid steel, expandable casing patch for operators who need a permanent, inexpensive casing patch solution that reliably restores well integrity.

11/21/2013

An Operator, in the Permian, discovered they did not obtain cement coverage along the entire length of the lateral after cementing their production casing.

11/01/2014

A Major Mid-Continent Operator needed a solution that could cover four perforations that were prematurely shot in the heel of the horizontal Woodford Shale well.  The ESeal HP Liner was successfully tested to 13,500 psi and passed 31 fracturing stages to re-establish the fracturing program. 