Challenge: Design and implement a field-level remediation plan using cased-hole SET® Solid Expandable Tubular technology to facilitate production restoration.

05/05/2009

To completely isolate the main pay zone (MPZ) from lower residual oil zone (ROZ) with options to set conventional liner in future if needed for conformance work. Installation of 5-1/2” x 7”, 23 lb ESeal Liners to isolate the upper perforations in each well would enable injection through newly-...

07/16/2010

A leading onshore natural gas producer working Northern Louisiana experienced problems along the vertical section of a horizontal development well.

Enventure deployed two ESeal Liners enabling them to continue the planned completion.

12/07/2007

As part of a multi-well program, isolate severe water-thief zones in a field where squeezing, casing patches and dual packer isolation assemblies rarely worked. The solution increased production and ultimately resulted in higher reserves.

09/01/2013
In the Marcellus Shale, fracturing rates and pressures can be substantial, but there are other problems also associated with completing these wells, which can promote casing failure or compromise the pressureintegrity of a well. A...
02/09/2014

A major operator in the Eagle Ford began a well recovery program to re-activate over 30 wells that stopped producing due to compromised well integrity (leaks).

02/18/2015

A major Operator in the Marcellus required a solution to seal squeeze perforations which would have to withstand high pressure frac operations. The area Regulatory Agency had suspended operations, not allowing completion of the well due to poor cement behind the production casing. The Operator...

02/12/2009

The Operator utilized Enventure's ESeal Liner expandable technology to isolate zones and provide a high-pressure environment for an aggressive re-frac program. The treatments paid out in ~2 months and increased production 700% where cement squeezes failed.